Your cart is currently empty!
Categories
Recent Posts
- Elevate Your Brand: The Power of Multi-Level Exhibit Architecture in China
- 20 Years of Excellence: Why Panda Expo China is the Trusted Stand Builder for International Food Pavilions
- Choosing the Right Exhibition Stand Builder in China: Your Ultimate Guide to Trade Show Success
- Exhibition Stand Construction Calendar 2026 from shanghai new international expo centre
- Panda Expo China: DAVIS’s Long-Term Exhibition Stand Partner
Archive
Tags
Access the Exhibition Venue for Work During Setup Period in China Air Cargo China BEIJING booth construction Booth Design for Trade Shows in China Booth Setup in Chinese Exhibition Venues challenges in building and constructing a food exhibition booth CHINAPLAS CIPS custom exhibition stand builders exhibition exhibition booth construction exhibition booth design exhibition booth in qingdao exhibition stall in qingdao Exhibition Stand Construction EXHIBITION STAND DESIGN exhibition stand designers and builders expo stand builders expo stand design fhc china Food Booth Construction Guangzhou Exhibition Booth Construction Guangzhou Exhibition Booth Construction Services HONG KONG Panda Expo Panda Expo China pavilion expo stand construction in china SHANGHAI singapore tradeshow list 2026 Sports Events in China tradeshow booth in qingdao tradeshow in guangzhou tradeshow in india tradeshow in japan tradeshow in shanghai tradeshow in vietnam tradeshow list in Hong Kong tradeshow list in indonesia 2026 tradeshow list in shanghai china 2026 tradeshow list in south korea TRADE SHOW LIST 2025 in china vinexpo asia Vinexpo Asia Hong Kong 2026 Exhibition Stand Construction we are hiring
Social Links

Sial China 2025 Shanghai: Booth Height Requirements & Approval Guide
Booth Height Classification & Core Requirements for Sial China 2025
1. Bare Booth with Height Below 4.5m
Online Drawing Submission System
ohss.opt-safe.cn/sial2025. The account and password for submission are the same as those used for the official contractor’s submission system, so exhibitors are advised to confirm the account information with their designated contractor in advance to avoid login issues.Required Drawing Materials
-
Overall effect drawing of the exhibition booth (including front and two side views)
-
Elevation dimensions drawing (with clear numerical markings of booth size and height)
-
Connection node diagram of main components
-
Exhibition booth planning instructions and detailed list of construction materials
-
Front and side elevation drawing
-
Sectional drawings
-
Structural drawings
-
Flame retardant test reports for carpets and floors
-
Stamped receipt of the payment notice
2. Bare Booth with Height of 4.5m or Above
Payment and Fee Standards for Sial China 2025 Booth Approval
-
For bare booths below 4.5m:
-
Booth Design Drawing review and on-site management service fee: 6.0 RMB per square meter
-
Booth Design Drawing Review Management fee: 15 RMB per booth
-
-
For bare booths of 4.5m or above:
-
One-floor booth approval fee: 25.00 RMB per square meter
-
Two-floor booth approval fee: 50.00 RMB per square meter
-
Key Precautions for Booth Approval
-
Submit drawings as soon as possible: Upload the booth design drawings to the designated system (OptSafe or HanHai) in a timely manner. Delays in submission may result in failure to pass approval on time, which will impact subsequent entry and setup work.
-
Truthfully register information: Accurately and truthfully register details of booth materials, including length, width, height dimensions, as well as the position and quantity of openings. False information may lead to approval rejection or on-site rectification.
-
Pay attention to approval feedback: OptSafe will reply via email within 5 working days to inform whether the drawings are approved. If no reply is received within this period, exhibitors should take the initiative to consult OptSafe to avoid missing follow-up procedures.
-
Complete payment and obtain approval documents: Only after the drawings pass the review and the drawing review fee is paid will exhibitors receive the “Approval opinions on booth design” issued by OptSafe. This document is a necessary condition for booth setup, so keep it properly.
-
No on-site drawing vetting: OptSafe will not conduct drawing review on-site. All approval procedures must be completed online in advance. Exhibitors should not wait until the last minute to handle the approval.